How to debug and install the full-automatic hydraulic integrated lifting column


Release time:

2023-02-15

As the maintenance equipment of some major places, the automatic hydraulic lifting column is more and more popular with everyone. Many customers do not know how to debug and install the automatic hydraulic integrated lifting column. The following is an answer for everyone.

As the maintenance equipment of some major places, the automatic hydraulic lifting column is more and more popular with everyone. Many customers do not know how to debug and install the automatic hydraulic integrated lifting column. The following is an answer for everyone.

 

全自动液压升降柱安装调试


Installation and commissioning requirements:
1. Digging foundation pits: digging foundation pits according to the overall dimensions of the product. The size of foundation pits: length: determining the size according to the road conditions on site; Width: 600 --- 800mm; Depth: 1400mm (including 300mm seepage layer);
2. Make a seepage layer: after mixing sand and gravel, pad up from the bottom of the foundation pit to make a 300mm seepage layer. The seepage layer is paved and compacted to prevent the equipment from sinking. (If the conditions are available, gravel below 10mm can be selected instead of sand.) According to the different circumstances of the region to choose whether to do drainage;
3. Unload the outer barrel of the product for leveling: unload the outer barrel of the product with hexagon socket, place it on the seepage layer, adjust the levelness of the outer barrel, make the upper surface of the outer barrel slightly higher than the ground plane by 3~5mm, and weld and reinforce the outer barrel with steel bars to prevent tilting;
4. Embedded pipe: embedded pipe threading pipe according to the position of outlet hole reserved on the surface of outer barrel. The diameter of the threading pipe is determined according to the number of lifting columns. Under normal circumstances, each lifting column needs a 3*1.5 power cord and a 2*0.75 pressure relief solenoid valve control line. If there is a lamp belt, if there is another 2*0.5 power cord, the specific use should be determined before construction according to the needs of customers and the difference of power distribution;
5. Debugging: Connect the circuit to the equipment, carry out ascending and descending operations, observe the ascending and descending conditions of the equipment, adjust the lifting height of the equipment, and check whether the equipment leaks oil;
6. Fixing equipment and pouring: Put the equipment into the pit, backfill a proper amount of sand, fix the equipment with stones, and then pour slowly and evenly with C40 concrete until it is level with the upper surface of the equipment.






 

 

 

Hebei Qi Xinlong Intelligent Technology Co., Ltd. is a research and development, design, production, sales and service in one of the anti-terrorism equipment manufacturers. Main products include: automatic lifting column, semi-automatic lifting column,Hydraulic lifting columnLandscape fixed column, flap barricade, tire breaker, etc. Tel: 15531750999.

Key words:

Installation and commissioning of automatic hydraulic lifting column


©2022 Hebei Qi Xinlong Intelligent Technology Co., Ltd. All Rights Reserved