Installation method of lifting column
Release time:
2022-03-07
What is the installation method of the lifting column? The following is a small series for everyone to answer.
What is the installation method of the lifting column? The following is a small series for everyone to answer.

1. Foundation pothole excavation:
Dig the foundation pit according to the overall dimensions of the product. The size and length of the foundation pit shall be determined according to the road conditions on site. Width: 800mm; Depth: 1400mm (including 300mm seepage layer).
2. Make seepage layer:
After mixing sand and gravel, pad up from the bottom of the foundation pit to make a 300mm seepage layer. The seepage layer is paved and compacted to prevent the equipment from sinking. (If the conditions are available, gravel below 10mm can be selected instead of sand.)
According to the different circumstances of the region to choose whether to do drainage.
3, remove the product outer cylinder leveling:
Remove the outer barrel of the product with hexagon socket, place it on the seepage layer, adjust the levelness of the outer barrel, and make the upper surface of the outer barrel slightly higher than the ground plane by 3~5mm.
4. Embedded line pipe:
The threading pipe shall be embedded according to the position of the outlet hole reserved on the surface of the outer barrel. The diameter of the threading pipe is determined according to the number of lifting columns. In general, the specifications of the cables required for each lifting column are 4*1.5*1 and 8*0.75*1. The specific use should be based on the needs of customers and the power distribution. Different, determined before construction.
5. Debugging:
Connect the circuit to the equipment, perform lifting and lowering operations, observe the lifting and lowering conditions of the equipment, adjust the lifting height of the equipment, and check whether the equipment has oil leakage.
6. Fixed equipment and pouring:
Put the equipment into the pit, backfill a proper amount of sand, fix the equipment with stones, and then pour slowly and evenly with C40 concrete until it is level with the upper surface of the equipment. (Note: The column must be fixed during pouring to prevent movement and dislocation to tilt it)
Hebei Qi Xinlong Intelligent Technology Co., Ltd. is a research and development, design, production, sales and service in one of the anti-terrorism equipment manufacturers. Main products include: automatic lifting column, semi-automatic lifting column, landscape fixed column, flap barricade, tire breaker, etc. Tel: 13930748833.
Key words:
Lifting column installation method
Previous Page
Next Page
Previous Page:
Next page:
recommend News
Advantages of electric lifting column
2024-03-01
Maintenance of electric lifting column
2024-02-29